Space Only Rules & Regulations
These guidelines ensure a welcoming, non-intimidating event with excellent sight lines and traffic flow.
Essential Design Requirements
- Construction: Space only exhibitors must arrange all electrical mains, fittings, carpets, and walling independently.
- Wall Heights: Adjoining walls are compulsory (min 2.5m). Walls exceeding 2.5m must be finished in a plain neutral colour up to 4m.
- Structural Approval: Structures over 4m high require structural engineer approval (min fee £290 + VAT).
- Full Walling: Any build over 1.2m is considered full walling. Max run of 3m of full walling per open side, separated by at least 1m of clear or low (1.2m) space.
- Transparency: Clear glazing must remain 100% transparent. No tints, frosting, or blinds are permitted.
- Platforms: Platforms over 38mm require a disabled access ramp with handrails in a contrasting colour. All platform edges must be rounded to prevent trips.
- Super Platforms: Platforms over 600mm are complex structures and require full structural details for approval.
Lighting, AV, and Logistics
- Lighting Rigs: Must be placed at least 6m from the hall floor and installed by authorized venue contractors.
- AV Equipment: Speakers must be angled inwards towards the centre of the stand to avoid noise nuisance.
- Flooring: Carpets must comply with BS 4790. Ensure steel frameworks have adequate base plates to protect the venue floor.
Submission of Plans
All space only exhibitors must submit the following by Monday 1st September:
- Stand plans in English, including all dimensions to a clearly recognisable scale.
- Side elevations, front elevation, and a plan view.
- Full details of fabrics and materials being used.
- Risk assessment for the build and breakdown period.
- Risk assessment for the open period.
- Method statement.
- Construction Phase Plan.
- CDM Sign off Sheet.
- Structural calculations (for complex structures only).
- Health & Safety policy, if relevant.
- Copy of insurance policy showing public liability cover of up to £2m.
Submitted Health & Safety Declaration
Stands cannot be constructed onsite without a stand approval notice being issued. Full Plans should be submitted to: operationsteam@markallengroup.com for review and approval.